Friday, 9/5/2008
We have investigated and have fully tested UPS-C9 with load fed from generator in isolated environment since 8pm (EST) on Thursday, while critical load is still fed from utility through external by-pass.
The test result was satisfactory and we will start preparation to put customer load from external by-pass to UPS-C9.
This will be happening in 12-24 hours.
We will keep you posted the schedule.
Peter Franconeri
Deputy Director
Facilities Engineering
TELEHOUSE America, Inc.
7 Teleport Drive, Staten Island, NY 10311
Tel 718-355-2530
Fax 718-355-2517